Friday, March 7, 2014

Status Report for week 6

Status report for week 6.
ALL the progress!
  1. Tasks accomplished
    1. We've completed and submitted our 1st full deliverable
    2. We've completed our 2nd deliverable.
    3. All downloaded the Android SDK and associated Eclipse version
  2. Tasks In Progress
    1. Minor changes to our 2nd deliverable and submit
    2. Develop the application
  3. Tasks Planned For the Next Two Weeks
    1. Development
  4. Issues
    1. None so far.
  5. Metrics
    1. Our group has contributed to the deliverables fairly evenly.
    2. Development metrics will be measured by commits to the repository and line-of-code changes, as well as interfaces assigned to specific team members.